Lewis and Clark finalizes Water Pipeline to Madison

Lewis and Clark Regional Water has finished the pipeline into the Madison area. The pipeline project reached completion on March 1 on the 16.1 miles of 16-inch PVC pipeline for Madison –

Segments 3B & 4. The pipeline deadline was originally scheduled for August of 2024. 

 

The DN Tanks are still under construction and will store one million gallon ground storage, the reservoir a few miles east of Madison. The project could be completed as early as May of 2024 

 

As the Lewis and Clarke water system reaches completion they also spoke on the the third and final phase which would involve finishing their water treatment plant they recently received a $103,669,000 contract to PKG of Fargo for the third and final phase of the project.